Please ensure Javascript is enabled for purposes of website accessibility
Kashagan Oil Field (Kazakhstan)

Kashagan Oil Field (Kazakhstan)

280 MW natural gas fired combined cycle power station and utilities area. Gas and steam turbines.

  • Solution: Execution of all civil works, steel structure, mechanics, electrical erection, piping, instrumentation, painting and insulation works to build a 280 MW natural gas fired combined cycle power plant composed of gas turbines and steam turbines. Supplying power for Trench 1 and 2 of Kashagan Petroleum Area. Supply of pipes, valves, fire-fighting systems, insulation material, structural steel and HVAC systems. Installation of insulation, HVAC and structural steel. Painting works and fire-proofing.
  • Project: Engineering, Procurement, Construction, (EPC

Challenges

Despite challenges related to remote area travel restrictions, civil unrest, and a man power shortage, the project was completed and showing excellent results.